Amazon Ads Immersion Day: Los Angeles — 13-week production timeline
Production started May 29, 2026 · Live August 28, 2026.
Current position
Week 8 of 13
Slippage flagged
Workback heads-up
1 flagged
1 week flagged for review:
- Week 9 — All large-format graphic elements approved → production at risk · approval slipping
AI surfaces the slips · producers decide push-back, escalate, or absorb.
13-week canonical timeline
Standardized across every event in the program · custom event-specific milestones layered under each canonical week
Week 1 of 13
May 29
Done- Alignment on scope
- Keynote/breakout programming
- Creative concepting
- Space planning
- Site visit
Week 2 of 13
Jun 5
Done- Alignment continued
- Programming refinement
- Creative concepting
Week 3 of 13
Jun 12
Done- R1 Creative & Logistics presented
- Content & show development commences
Week 4 of 13
Jun 19
Done- Feedback & refinement
- Production & 3P staffing vendors finalized
Week 5 of 13
Jun 26
Done- R2 Creative & Logistics presented
- Feedback & refinement
Week 6 of 13
Jul 3
Done- R3 Creative & Logistics presented
- Feedback & refinement
Week 7 of 13
Jul 10
Done- Final Creative approvals requested
Week 8 of 13
Jul 17
In progress- All fabrication & scenic elements approved → production
Week 9 of 13
Jul 24
At risk- All large-format graphic elements approved → production
Week 10 of 13
Jul 31
Upcoming- A/V & technical orders finalized
- All catering finalized
- Content/digital assets finalized
Week 11 of 13
Aug 7
Upcoming- Final production planning
- Security & staffing plans shared
- Initial production schedule shared
- Final event collateral approved
Week 12 of 13
Aug 14
Upcoming- Shipping commences
- Crisis management & ops plans shared
- Final scripts & content elements delivered
Week 13 of 13
Aug 21
Upcoming- Pre-site call with all stakeholders
- Final speaker prep